Working along an operational jetty
Calor’s Canvey Island terminal has loading-arm equipment, pipework and electrical systems along an exposed marine jetty. JCOS supported the EC&I packages for the jetty and heaters, working with the existing site equipment and access arrangements.

Cable routes and field equipment
JCOS installed local junction boxes and operator stations, completed the main cable pulls and dressed the cables into the available containment routes. Work included glanding and termination at the junction boxes and local equipment room.
Specialist access was used on sections away from the walking deck. Field connections and commissioning were sequenced around the pipework and heater releases.