Gemini extraction fan control panel
JCOS designed and built the control panel for the Gemini extraction fan at RAF Fairford. The package included electrical installation, testing, certification and handover documentation.
A separate BMS pump work package at Yeovilton also included a JCOS-built control panel.
From planned maintenance to wider EC&I delivery
JCOS first supported Bulk Meter Services through planned preventative maintenance at MOD sites. The relationship grew into wider EC&I, hazardous-area and commissioning support at RAF Fairford and other defence locations, delivered by personnel experienced in working on live MOD sites.
Hazardous-area asset register and risk-based repairs
JCOS built the ATEX asset register and delivered more than 2,000 C2 repairs across live fuel installations. Each defect was reviewed, risk assessed and prioritised before repair.
The team completed electrical works and supported inspection, testing, commissioning and operational handover. Other packages included fire and gas upgrades, control-system I/O testing, floodlighting and replacement of non-compliant ATEX equipment.
Engineering records for operation and assurance
JCOS produced supporting schematics, loop drawings, intrinsic-safety calculations, cable schedules and commissioning records. Keeping the same team through survey, remediation, installation and commissioning reduced handover gaps and gave BMS a controlled technical record for future operation and maintenance.